‘Soft-opening’ of Barrington rec centre planned for December

Delays continue for Barrington’s new recreation centre.

Originally slated to open in the spring, a soft-opening is now planned for December.

The $6.9 million centre is an add-on to the arena on Sherose Island.

Barrington warden Shaun Hatfield says construction delays are common.

“Whether it’s a residential home or something privately even, you’re waiting for tradespeople to be able to converge, or supplies to arrive sometimes,” said Hatfield.

The Barrington Recreation Centre is an add-on to the Sandy Wickens Memorial Arena (Acadia News Photo)

Construction started in April, 2024 on the facility.

Hatfield says it’s going to create spaces for events and physical activity.

“It’s got a walking and running track, a program kitchen, 4,000 square feet of multi-purpose rooms for activities and meetings.”

A full opening will happen in early 2026.


  • Kevin Northup

    Kevin Northup has been a reporter and news anchor for more than 15 years. He is based in Yarmouth and covers stories locally and across Nova Scotia. Contact Kevin at northupk@radioabl.ca.

    View all posts

Do you have a news tip?

Submit to NSNews@radioabl.ca.

loader-image
Bridgewater, CA
4:09 am, Apr 11, 2026
weather icon 4°C | °F
L: 4° H: 4°
overcast clouds

What’s Trending